[Model] PrecedenceConstrainedScheduling #501

@isPANN

Description

@isPANN

Motivation

PRECEDENCE CONSTRAINED SCHEDULING (P193) from Garey & Johnson, A5 SS9. A fundamental NP-complete multiprocessor scheduling problem: given unit-length tasks with precedence constraints, m processors, and a deadline D, can all tasks be scheduled to meet D while respecting precedences? NP-complete via reduction from 3SAT (R138) [Ullman, 1975]. Remains NP-complete even for D = 3 [Lenstra & Rinnooy Kan, 1978a]. Solvable in polynomial time for m = 2 [Coffman & Graham, 1972], for forest-structured precedences [Hu, 1961], and for chordal complement precedences [Papadimitriou & Yannakakis, 1978b].

Associated rules:

  • R138: 3SAT → Precedence Constrained Scheduling (this model is the target)

Definition

Name: PrecedenceConstrainedScheduling

Reference: Garey & Johnson, Computers and Intractability, A5 SS9

Mathematical definition:

INSTANCE: Set T of tasks, each having length l(t) = 1, number m ∈ Z+ of processors, partial order < on T, and a deadline D ∈ Z+.
QUESTION: Is there an m-processor schedule σ for T that meets the overall deadline D and obeys the precedence constraints, i.e., such that t < t' implies σ(t') ≥ σ(t) + l(t) = σ(t) + 1?

Variables

  • Count: n = |T| (one variable per task, representing the time slot it is assigned to)
  • Per-variable domain: {0, 1, ..., D-1} — the time slot in which the task is executed (0-indexed)
  • dims(): vec![deadline; num_tasks] — each task is assigned to one of D time slots
  • Meaning: σ(t_i) ∈ {0, ..., D-1} is the time slot assigned to task t_i. At most m tasks can be assigned to the same time slot (processor capacity). If t_i < t_j in the partial order, then σ(t_j) ≥ σ(t_i) + 1. A valid schedule assigns all n tasks to time slots in {0, ..., D-1} respecting both processor capacity and precedence constraints. This is a satisfaction (decision) problem with Metric = bool.

Schema (data type)

Type name: PrecedenceConstrainedScheduling
Variants: none (tasks are unit-length; no type parameters)

Field Type Description
num_tasks usize Number of tasks n =
num_processors usize Number of processors m
deadline usize Global deadline D
precedences Vec<(usize, usize)> Precedence pairs (i, j) meaning t_i < t_j

Size fields: num_tasks, num_processors, deadline

Notes:

  • This is a satisfaction (decision) problem: Metric = bool, implementing SatisfactionProblem.
  • Key getter methods: num_tasks() (= |T|), num_processors() (= m), deadline() (= D).

Complexity

  • Best known exact algorithm: The problem is NP-complete [Ullman, 1975]. For m = 2, the Coffman-Graham algorithm solves it in O(n^2) time [Coffman & Graham, 1972]. For fixed m ≥ 3, the complexity is open. For variable m, the problem is strongly NP-hard. Exact algorithms for general instances use branch-and-bound or ILP formulations. The problem is W[2]-hard parameterized by the number of processors [Bodlaender & Fellows, 'W[2]-hardness of precedence constrained K-processor scheduling,' Operations Research Letters, 18(2):93-97, 1995]. A fixed-parameter algorithm based on the width w of the precedence graph runs in O(n^3 + n · w · 2^{4w}) time [van Bevern et al., 2016]. The brute-force complexity is O(D^n) for assigning each of n tasks to one of D time slots, followed by feasibility checking.
    declare_variants! guidance:
declare_variants! {
    PrecedenceConstrainedScheduling => sat, "deadline ^ num_tasks",
}

This uses the brute-force O(D^n) bound for assigning each of n tasks to one of D time slots.

Extra Remark

Full book text:

INSTANCE: Set T of tasks, each having length l(t) = 1, number m ∈ Z+ of processors, partial order < on T, and a deadline D ∈ Z+.
QUESTION: Is there an m-processor schedule σ for T that meets the overall deadline D and obeys the precedence constraints, i.e., such that t < t' implies σ(t') ≥ σ(t) + l(t) = σ(t) + 1?

Reference: [Ullman, 1975]. Transformation from 3SAT.

Comment: Remains NP-complete for D = 3 [Lenstra and Rinnooy Kan, 1978a]. Can be solved in polynomial time if m = 2 (e.g., see [Coffman and Graham, 1972]) or if m is arbitrary and < is a "forest" [Hu, 1961] or has a chordal graph as complement [Papadimitriou and Yannakakis, 1978b]. Complexity remains open for all fixed m ≥ 3 when < is arbitrary. The m = 2 case becomes NP-complete if both task lengths 1 and 2 are allowed [Ullman, 1975]. If each task t can only be executed by a specified processor p(t), the problem is NP-complete for m = 2 and < arbitrary, and for m arbitrary and < a forest, but can be solved in polynomial time for m arbitrary if < is a "cyclic forest" [Goyal, 1976].

How to solve

  • It can be solved by (existing) bruteforce. (Enumerate all assignments of n tasks to D time slots; check processor capacity ≤ m per slot and precedence constraints.)
  • It can be solved by reducing to integer programming. (Binary ILP: x_{it} ∈ {0,1} = task i in time slot t; Σ_t x_{it} = 1 for each task; Σ_i x_{it} ≤ m for each slot t; precedence: Σ_t t·x_{jt} ≥ Σ_t t·x_{it} + 1 for each (i,j) ∈ precedences.)
  • Other: Coffman-Graham algorithm for m = 2 [Coffman & Graham, 1972]; Hu's algorithm for forest precedences [Hu, 1961].

Example Instance

Input:
n = 8 tasks: T = {t_1, t_2, t_3, t_4, t_5, t_6, t_7, t_8}
m = 3 processors, D = 4 time slots.
Precedences:

  • t_1 < t_3
  • t_1 < t_4
  • t_2 < t_4
  • t_2 < t_5
  • t_3 < t_6
  • t_4 < t_7
  • t_5 < t_7
  • t_6 < t_8
  • t_7 < t_8

Feasible schedule:

Time slot Tasks (up to 3 per slot)
1 t_1, t_2
2 t_3, t_4, t_5
3 t_6, t_7
4 t_8

Check precedences:

  • t_1(1) < t_3(2) ✓, t_1(1) < t_4(2) ✓
  • t_2(1) < t_4(2) ✓, t_2(1) < t_5(2) ✓
  • t_3(2) < t_6(3) ✓, t_4(2) < t_7(3) ✓
  • t_5(2) < t_7(3) ✓, t_6(3) < t_8(4) ✓
  • t_7(3) < t_8(4) ✓

Processor capacity: max tasks per slot = 3 ≤ m = 3 ✓
All tasks complete by slot 4 = D ✓

Answer: YES — a valid 3-processor schedule meeting deadline D = 4 exists.

Metadata

Metadata

Assignees

No one assigned

    Labels

    GoodAn issue passed all checks.modelA model problem to be implemented.